Client| Programmed + City of Casey

Circumstance

With the main Athletics pavilion nearing completion, the client requested additional Entry Box building. With the tight time frames seeed was engaged to explore possible designs and react to the project program.

seeed’s Response

Using 3D modelling seeed investigated several design options, which was forward through to the client, where a preferred design was chosen. With the preferred design locked in seeed proceeded to finalize the design to gain client sign off. Design Sign Off was archived in a period of 48 hrs from the initial engagement; this was only possible with the use of 3D designing and proactive collaborative virtual relationship with the client.

The project underwent Contract Documentation and issued for tender within a week. This enable to client to tender to project and award in accordance with it’s corporate government responsibilities; with the construction works completed without causing any delay to the external landscape works under a separate contract.